October 2026

Warrington MSA Works – Progress Update

Work continues across all three phases:

Phase 1: S278 works are now nearing completion for RSA stages.

Phase 2: Development platform complete with the amenity building and external works programme now approaching the halfway point.

Phase 3: Work on the hybrid fuel filling station tank vault has commenced.

Great to see the project progressing and each phase reaching these key milestones.

Project News
May 2026

Phase 2 at Prologis Park Beddington Lane, Croydon

We’re proud to announce that Phase 2 at Prologis Park Beddington Lane, Croydon has achieved BREEAM Outstanding certification.

The development comprises three separate warehouse/production units — DC5A/5B, DC6 and DC7 — delivering a total of 96,000 sq ft, alongside office accommodation and associated external works including a new site entrance.

Achieving BREEAM Outstanding reflects the Clients commitment to delivering high-performance, sustainable industrial space and represents a significant milestone for the scheme.

A fantastic achievement by the whole team involved in the design, delivery and collaboration across the project.

Company News
March 2026

CSA Now on Constellia

We’re pleased to announce that Christopher Smith Associates has successfully completed the Constellia onboarding process and is now officially an Approved Supplier on the Constellia Marketplace.

CSA are proud to offer a range of services nationwide as part of this appointment including:

Quantity Surveying
Employers Agent
Contract Administration

Project News
February 2026

Start on Site at Plot 10, Patchway Industrial Estate

Great progress is being made at Plot 10, Patchway Industrial Estate, Bristol, where Bath Demolition is undertaking the site clearance and demolition of the former J Sainsbury’s logistics depot and associated external areas, which can be seen here: https://lnkd.in/erisCRzs

This important phase of works is paving the way for the delivery of two best-in-class industrial and logistics units, targeting BREEAM Outstanding certification.

Once complete, the units will be delivered to a high-quality Cat A specification, setting a strong benchmark for sustainable industrial development in the region

Watch this space!

Project News
February 2026

Phase 3 at Longwell Green

Commencement of Phase 3 works at Longwell Green Retail Park has now begun as part of a comprehensive full-site redevelopment programme. Phase 3 comprises the demolition of the existing trade counter units in preparation for the construction of three new drive-thru units. CSA are appointed as Quantity Surveyor and Employer’s Agent on behalf of CBRE Global Investors.

drone view of project
Project News
January 2026

2050b Underway at DP World London Gateway

Site commencement at DP World London Gateway on the new 2050b Unit, providing an 800,000sqft logistics centre to be built to suit the tenant. CSA are providing project management, employers agent and quantity surveying services as part of our ongoing relationship with DP World

Project News
January 2026

Successful Completion of Valor Tottenham Project

This project comprised the demolition of existing industrial buildings and the construction of two new Grade A units across separate sites: Unit 1 (60,000 ft²) and Unit 2 (12,000 ft²). Both units were designed with a strong focus on sustainability, incorporating PV panels, EV charging infrastructure, and green roofs to achieve BREEAM Excellent and EPC A+ ratings.

CSA were appointed by Valor Real Estate Partners LLP to provide Cost Management and Employer’s Agent services across all RIBA work stages, ensuring successful delivery from project inception through completion.